Case study · New plant · Brownfield · Vertical layout · Automation

Start-up of a new
production plant.

A new plant for a manufacturer of supplements and pharmaceuticals — with the production concept changed from linear on a single level to a vertical process layout.

Plant area
10,000 m²
investment value up to PLN 100M
To first production
8 months
from the start of the engagement
Production lines
3 + 1
3 relocated + 1 new
Automation
4 of 4
lines with automated packaging and palletising

A new building.
A new production concept.

The project covered fitting out a finished building with process equipment, layout and production organisation — together with end-of-line automation. Some orders and building works were already under way.

As a pharmaceutical production plant, every process decision — layout, flows, building services — went through quality and GMP requirements. The investment was one of more than 100 projects run in the organisation over two years.

One person
for one plant.

The company was running many investments in parallel, and its directors were also responsible for technical departments and maintenance in operating plants. The new plant got a person dedicated solely to it — with the task of bringing it into production.

What the new
plant delivered.

A process consolidated in one place and automated end-of-line brought:

The whole plant,
from concept to acceptance.

From horizontal to vertical.

Moving the lines did not mean recreating the old set-up. Production had previously run linearly, on a single level. In the new plant it was redesigned as a vertical process layout, with materials moving between levels.

Everything else in the project followed from this change: layout, flow of materials and people, building services and the connection to the warehouse. Every line — relocated and new — was fitted into the same layout.

Every line ends
automatically.

A separate, parallel workstream of the project was end-of-line automation: packaging and palletising for all four lines — the new one and the three relocated from other plants. The relocated lines received automation designed from the start for the target layout.

Result: higher throughput and fewer errors at the end of the line — where, in pharmaceutical production, every packaging mistake matters for batch quality and compliance.

A plan, a team
and a shared rhythm.

Scopes and plan. All tasks, orders and contractor commitments — more than 200 items — were brought together in one place. On that basis, work scopes, a requirements list and a plan for the whole undertaking were created.

Project team. The people involved in the investment formed one team — with clear roles and a shared plan. Success factors were defined and used to measure progress.

Working to plan. Contractors worked to shared schedules. Progress was monitored continuously and contracts were settled on the basis of data.

Production as the project's client. Requirements from production departments were gathered and approved before execution. As a result, the layout and flows were designed around how the plant really works.

Production
started.

The plant started production in the new layout. Packaging and palletising automation on all lines delivered higher throughput and fewer errors. The following months focused on optimising plant operations and adding further lines.

The project was delivered by the team — and that is the most important part of this story. The Project Manager's role was to turn the knowledge of many people and the work of many companies into one plan, one team and one working rhythm.

Starting up a plant
or relocating lines?

Let's talk about where your project stands — and what needs to be put in order for production to start on time.

Book a 20-minute call artur@arturwinkowski.pl